Japan’s seven big automakers are extending nationwide production shutdowns amid growing concern about supply chain interruptions, power shortages and export difficulties following the massive earthquake and tsunami that hammered northern Japan, killing thousands.
@funkmasterflex
Toyota Motor Corp., one of the few automakers with a major manufacturing presence in the quake zone, suspended all manufacturing – at both assembly and parts plants – on Monday and extended the shutdown through at least Wednesday as an added precaution.
The company will lose output of roughly 40,000 vehicles over the three-day period, spokesman Dion Corbett said.
Broadening impact
Carmakers are halting production – even at plants not affected by Friday’s 8.9-magnitude monster quake – partly to give workers time to regroup with families. Thousands of people in northern Japan are still unaccounted for, as authorities predict a death toll exceeding 10,000.
But the country’s supply chain has also been slammed – with automakers still unable to make contact with some parts makers in the quake zone three days after Friday’s disaster. There is also concern about export shipments being interrupted by tsunami damage to the nation’s ports.
U.S. production may even be hit if plants there can’t get parts normally imported from Japan.
Mitsubishi Motors Corp. had already announced it would stop production at all its factories through Tuesday. By Monday evening, Honda, Nissan, Subaru and Suzuki, said shutdowns initially planned only for Monday would be extended to later in the week.
Mazda, which continued output for a half-day Monday, joined the wave of suspensions.
Missing in action
All plants at Honda Motor Co. will remain off line through at least Sunday, March 20. It expects to lose about 16,600 units of auto production. About 2,500 of those vehicles – including the Fit small car, Insight hybrid and Acura RL – would have been bound for the United States.
Honda has 113 suppliers in the quake zone and still can’t get in touch with 44 of them.
“We cannot complete a car, even if one or two parts are missing,” Honda spokesman Keitaro Yamamoto said. “So it’s better that we stop production altogether.”
Nissan is closing its Tochigi assembly plant and an engine plant – both in the quake zone – at least through Friday. Elsewhere in the country, it is closing four assembly plants and one engine factory through at least Wednesday. The company wouldn’t say how many units of production it expects to lose or how its U.S. exports may be affected.
Suzuki Motor Co. announced it would extend its suspension through Wednesday and reassess then.
Even Mazda Motor Corp., whose base of operations lies in far-western Japan where the quake was barely felt, said it was suspending the Monday night shifts at its two assembly plants and asking workers at both shifts to stay home Tuesday and Wednesday.
“We are expecting shortages of certain parts, such as steel plates and brake parts, to name a few,” spokesman Kotaro Minagawa said.
Mazda’s shutdown affects every model it sells in the Untied States, except the Mazda6 sedan, which is made in Michigan at its joint venture plant with Ford Motor Co.
Fuji Heavy Industries Ltd., maker of Subaru brand cars, was among those extending Monday’s shutdown through Wednesday. That move affects U.S. exports of the Forester and Impreza.
Mitsubishi said it had secured enough parts to resume production Wednesday. But production plans for Thursday and beyond would have to be assessed at a later date, it warned.
Overseas threat
Even U.S. output at Japanese-brand plants may be hurt if parts exports are pinched.
“Overseas production could be affected as well if shutdowns become prolonged, as core components such as engines and transmissions are supplied to overseas vehicle factories from Japan,” predicted Kohei Takahashi, an auto analyst with J.P. Morgan Securities in Tokyo.
“Given the 20,000 to 30,000 parts that go into making an automobile, and the difficulty of procuring even basic materials, we do not foresee a return to normal production schedules anytime soon,” he wrote in a report, adding he saw little lingering long-term industry damage.
The looming memory is the supply chain breakdown triggered by an earthquake in Japan’s northern prefecture of Niigata in 2007. That quake damaged plants at just a handful of key suppliers, most notably the piston ring maker Riken. The ensuing parts shortage set back nationwide auto output by 125,000 units, notes Japan’s Nikkan Jidosha industry newspaper.
Even if the cars can be built, sending them overseas is another hurdle.
Nissan Motor Co.’s export facility at the Port of Hitachi, for example, was clogged with thousands of damaged or burned-out cars after being slammed by the tsunami’s wall of water. It is believed the inferno erupted after the cars were smashed together triggering fuel leaks.
Toyota said it was still gathering information on how its exports might be affected.
Power problems
Meanwhile, rolling power shutdowns throughout eastern Japan have been implemented by the local utility, Tokyo Electric Power Co., to save electricity. Power output capacity has been slashed because many generation plants – including nuclear – were damaged in the disaster.
Engineers are racing to prevent meltdowns in at least two reactors at one nuclear plant.
Authorities have expanded the evacuation zone to a 12-mile radius around one site. Small amounts of radiation are already leaking, following explosions at two of its reactors.
The planned blackouts have crimped business operations as well as interrupted train services, making it difficult for many employees to report to work. Reported gasoline shortages, triggered by damaged refineries, have further contributed to a logistical and transportation snarl.
Meanwhile, automakers are also concerned about additional damage to plants from strong aftershocks, which continued rocking the region through Monday evening, with new earthquakes cropping up in different regions of the country.
AN